Road Construction Projects

2026 Stoughton Construction Projects Coming Soon

2026 Stoughton Construction Project Information

Last Updated: June 9, 2026

Current Road Closure Information

2026 Project Status

Project Construction Limits Type of Improvement Project Status
Van Buren St Greig Trail To Kriedemen Pulverize-Road Diet Work to Begin in Late-June/Early July
Sidewalk Program North of Roby and West of Vergin Lake Sidewalk Replacement Work to Begin in August
Racetrack Rd (Joint Project with Town of Dunkirk) Hwy 51 to Hwy A Reconstruction Work to Begin in Early July
Taft St. Page to Wilson Reconstruction In Progress - Expected Completion: Mid to Late October
Wilson St Page to Taft Reconstruction In Progress - Expected Completion: Mid to Late October
Harding/Grant St Page To Wilson Reconstruction In Progress - Expected Completion: Mid to Late October
Sherman St Wilson to Harding Reconstruction In Progress - Expected Completion: Mid to Late October
Mckinley St Prospect To Grant Reconstruction In Progress - Expected Completion: Mid to Late October
Main Page Court All of Main Page Ct Pulverization and Rehabiliate In Design - Construction in Spring of 2027
Jefferson St Bridge Pedestrian Bridge Remove and Replace Bridge In Design - Construction in Spring of 2027
DOT PROJECT - Main St (Hwy 51)- Wall Fifth to Church Finish Wall and Sidewalk Complete
DOT PROJECT - Main St (Hwy 51) Harrison to B Reconstruction In-progress - Expected Completion: Early November