Friday, August 1st the contractor will be switching the access to the Hospital deliveries and the Skaalen area from Franklin St back to Morris. This switch to be in place for a few weeks.

2025 Stoughton Construction Project Status Update

2025 Stoughton Construction Project Status Update

Last Updated: July 29th
Project Name Location Status Timeline Notes
E. Main St (Hwy 51) - Stage 1 Spring Rd to Hwy N Complete March 24-June DOT Project
E. Main St (Hwy 51) - Stage 2 Hwy N to Church St Active June - Aug DOT Project
E. Main St (Hwy 51) - Stage 3 Church St to Fifth St Scheduled Aug - Nov DOT Project
S. Fourth St Milwaukee to Isham Active June 23-TBD DOT Project
Lincoln Ave Hwy B to Kriedeman Active June 16- August 18
Wilson St Lincoln to Van Buren Scheduled to begin Late July July 15- August 25
Van Buren St Roby to Kriedeman Scheduled to begin June 29 June 16- September 19
Roosevelt St Van Buren to Riverview Scheduled to begin June 16 June 16- September 17
Eisenhower Rd Van Buren to Lincoln Active June 16- September 17
Christiansen Way Norse Parkway to Mellum Contract Approvals Late Summer Slated to begin Late summer
Mellum Dr Norse Parkway to Page Contract Approvals Late Summer Slated to begin Late summer
Mandt Park Parking Lots and River Walk Active Spring Paving and Turf Restoration Underway
Rotary Park Pond Rehab Rotary Park Out for Bid June 24 TBD Conversion to a biobasin