Road Construction Projects

Interactive Construction Map
2025 Stoughton Construction Project Status Update

2025 Stoughton Construction Project Status Update

Last Updated: November 6
Project Name Location Status Timeline Notes
E. Main St Hwy 51 Detour Map Stage 1 Spring Rd to Hwy N Completed DOT Project
Stage 2 Hwy N to Church St Competed DOT Project
Stage 3 Church St to Fifth St Active Sept 15 - Late November Retaining Wall at 5th and Main St will resume in Spring of 2026....DOT Project
S. Fourth St Milwaukee to Isham Completed DOT Project
Lincoln Ave Hwy B to Kriedeman Completed
Wilson St Lincoln to Van Buren Completed
Van Buren St Roby to Kriedeman Completed
Roosevelt St Van Buren to Riverview Completed
Eisenhower Rd Van Buren to Lincoln Completed
Christiansen Way Norse Parkway to Mellum Completed
Mellum Dr Norse Parkway to Page Completed
Mandt Park Parking Lots and River Walk Active Spring 2026
Rotary Park Pond Rehab Rotary Park Completed Conversion to a biobasin