Road Construction Projects
Friday, August 1st the contractor will be switching the access to the Hospital deliveries and the Skaalen area from Franklin St back to Morris. This switch to be in place for a few weeks.
2025 Stoughton Construction Project Status Update
Last Updated: July 29th
Project Name | Location | Status | Timeline | Notes |
---|---|---|---|---|
E. Main St (Hwy 51) - Stage 1 | Spring Rd to Hwy N | Complete | March 24-June | DOT Project |
E. Main St (Hwy 51) - Stage 2 | Hwy N to Church St | Active | June - Aug | DOT Project |
E. Main St (Hwy 51) - Stage 3 | Church St to Fifth St | Scheduled | Aug - Nov | DOT Project |
S. Fourth St | Milwaukee to Isham | Active | June 23-TBD | DOT Project |
Lincoln Ave | Hwy B to Kriedeman | Active | June 16- August 18 | |
Wilson St | Lincoln to Van Buren | Scheduled to begin Late July | July 15- August 25 | |
Van Buren St | Roby to Kriedeman | Scheduled to begin June 29 | June 16- September 19 | |
Roosevelt St | Van Buren to Riverview | Scheduled to begin June 16 | June 16- September 17 | |
Eisenhower Rd | Van Buren to Lincoln | Active | June 16- September 17 | |
Christiansen Way | Norse Parkway to Mellum | Contract Approvals | Late Summer | Slated to begin Late summer |
Mellum Dr | Norse Parkway to Page | Contract Approvals | Late Summer | Slated to begin Late summer |
Mandt Park | Parking Lots and River Walk | Active | Spring | Paving and Turf Restoration Underway |
Rotary Park Pond Rehab | Rotary Park | Out for Bid June 24 | TBD | Conversion to a biobasin |