Road Construction Projects
2025 Stoughton Construction Project Status Update
Last Updated: June 9th
Project Name | Location | Status | Timeline | Notes |
---|---|---|---|---|
E. Main St (Hwy 51) - Stage 1 | Spring Rd to Hwy N | Active | March 24-June | DOT Project |
E. Main St (Hwy 51) - Stage 2 | Hwy N to Church St | Scheduled to beging June 23 | June - Aug | DOT Project |
E. Main St (Hwy 51) - Stage 3 | Church St to Fifth St | Aug - Nov | Aug - Nov | DOT Project |
S. Fourth St | Milwaukee to Isham | Mid June Start Date | TBD | DOT Project |
Lincoln Ave | Hwy B to Kriedeman | Scheduled to begin June 16 | June 16- July 31 | |
Wilson St | Lincoln to Van Buren | Scheduled to begin June 16 | July 15- August 11 | |
Van Buren St | Roby to Kriedeman | Scheduled to begin June 16 | June 16- August 19 | |
Roosevelt St | Van Buren to Riverview | Scheduled to begin June 16 | June 16- August 3 | |
Eisenhower Rd | Van Buren to Lincoln | Scheduled to begin June 16 | June 16- August 3 | |
Christiansen Way | Norse Parkway to Mellum | Contract Approvals | Late Summer | Slated to begin Late summer |
Mellum Dr | Norse Parkway to Page | Contract Approvals | Late Summer | Slated to begin Late summer |
Mandt Park | Parking Lots and River Walk | Active | Spring | Paving and Turf Restoration Underway |
Rotary Park Pond Rehab | Rotary Park | Out for Bid June 24 | TBD | Conversion to a biobasin |