Project Name Location Status Timeline Notes
E. Main St (Hwy 51) - Stage 1 Spring Rd to Hwy N Active March 24-June DOT Project
E. Main St (Hwy 51) - Stage 2 Hwy N to Church St Scheduled to beging June 23 June - Aug DOT Project
E. Main St (Hwy 51) - Stage 3 Church St to Fifth St Aug - Nov Aug - Nov DOT Project
S. Fourth St Milwaukee to Isham Mid June Start Date TBD DOT Project
Lincoln Ave Hwy B to Kriedeman Scheduled to begin June 16 June 16- July 31
Wilson St Lincoln to Van Buren Scheduled to begin June 16 July 15- August 11
Van Buren St Roby to Kriedeman Scheduled to begin June 16 June 16- August 19
Roosevelt St Van Buren to Riverview Scheduled to begin June 16 June 16- August 3
Eisenhower Rd Van Buren to Lincoln Scheduled to begin June 16 June 16- August 3
Christiansen Way Norse Parkway to Mellum Contract Approvals Late Summer Slated to begin Late summer
Mellum Dr Norse Parkway to Page Contract Approvals Late Summer Slated to begin Late summer
Mandt Park Parking Lots and River Walk Active Spring Paving and Turf Restoration Underway
Rotary Park Pond Rehab Rotary Park Out for Bid June 24 TBD Conversion to a biobasin