Bjoin Park Neighborhood
Project: Bjoin Park Neighborhood Improvements
Owner: City of Stoughton
Contract: 1-2026
Contractor: Fischer Excavating, Inc.
Below is a summary of work completed to-date and a summary of the Contractor’s anticipated work for the following week.
Work Completed for Week 3: June 1 - June 5
The contractor installed sanitary sewer on Wilson Street between Grant Street and Sherman Street.
Work Anticipated for Week 4: June 8- June 12
The contractor will continue with sanitary sewer installation in the park area between Wilson Street and Grant Street near Harding Street.
The contractor will continue with sanitary sewer installation on Harding Street between Grant Street and Page Street.
The City of Stoughton will continue with tree removal later in the week, the contractor will begin with water main construction on Harding Street.
Upcoming Work
Following completion of sanitary sewer construction on Harding Street and Wilson Street.
Traffic Control
Streets in the Bjoin Park neighborhood are closed to through traffic, but open to local traffic.
When construction crews are working in front of driveways, access will not be available.