Bjoin Park Neighborhood

Bjoin Park Project Phasing Map

Project: Bjoin Park Neighborhood Improvements

Owner: City of Stoughton

Contract: 1-2026

Contractor: Fischer Excavating, Inc.

Below is a summary of work completed to-date and a summary of the Contractor’s anticipated work for the following week.

Work Completed for Week 3: June 1 - June 5

  • The contractor installed sanitary sewer on Wilson Street between Grant Street and Sherman Street.

Work Anticipated for Week 4: June 8- June 12

  • The contractor will continue with sanitary sewer installation in the park area between Wilson Street and Grant Street near Harding Street.

  • The contractor will continue with sanitary sewer installation on Harding Street between Grant Street and Page Street.

  • The City of Stoughton will continue with tree removal later in the week, the contractor will begin with water main construction on Harding Street.

Upcoming Work

  • Following completion of sanitary sewer construction on Harding Street and Wilson Street.

Traffic Control

  • Streets in the Bjoin Park neighborhood are closed to through traffic, but open to local traffic.

  • When construction crews are working in front of driveways, access will not be available.