Roosevelt Street

Scheduling

(Subject to Change)

June 16- Construction Start

July 14 - Sidewalk Work

July 21- July 29: Driveway, Curb removals and replacement

August 1- 5: Turf Restoration, Topsoil seed and mulch

August 8- 9: Pulverize

August 10-19: Grade, proof roll, adjust water boxes

Roosevelt Street Road Construction Project 2025