North Van Buren Street
Construction Update
Work Completed for Week 13: September 15 - September 19
The contractor completed fine grading of the pulverized material on Roosevelt Street and Eisenhower Road.
The contractor placed both layers of asphalt pavement on Roosevelt Street and Eisenhower Road.
The contractor made final preparations for upper layer (surface paving) on Van Buren Street.
Work Anticipated for Week 14: September 22 - September 26
The contractor intends to place the upper layer of asphalt pavement on Van Buren Street on Monday September 22nd.
The contractor intends to complete the new pavement markings on Van Buren Street by mid-week.
Upcoming Work
Following placement of pavement markings, the project will be substantially complete.
Traffic Control
Van Buren Street, Roosevelt Street, and Eisenhower Road are closed to through traffic, but open to local traffic.
Expect delays and driveway access difficulties during paving. The new pavement must be allowed to cool and harden before traffic is allow on it to avoid damage.