North Van Buren Street
Construction Update
Work Completed for Week 9: August 18 - August 22
Heavy rain again required cleanup of the project area early in the week and delayed planned grading and paving activity.
The contractor resumed grading and rolling of pulverized material in the middle of the week in preparation for paving.
The contractor placed the lower layer of asphalt pavement on Van Buren Street on Friday.
Work Anticipated for Week 10: August 25 - August 29
The contractor may begin curb and gutter removal on Roosevelt Street and Eisenhower Road next week.
Upcoming Work
Following curb and gutter construction on Roosevelt Street and Eisenhower Road, turf restoration will be completed. The street pulverization and grading process will then begin
Traffic Control
Van Buren Street, Roosevelt Street, and Eisenhower Road are closed to through traffic, but open to local traffic.
Expect delays and driveway access difficulties during paving.