Mellum Drive
Work Completed for Week 3: September 15 - September 19
The contractor completed all concrete replacements.
The City of Stoughton used its equipment and staff to pulverize the remaining asphalt pavement.
The City continued working on rough grading and removal of excess pulverized material.
Work Anticipated for Week 4: September 22 - September 26
The City of Stoughton will continue with excavation and placement of base course to address areas of unstable subgrade.
Upcoming Work
The contractor will adjust manhole castings and valve boxes to the new pavement elevation.
The contractor will fine grade the pulverized material in preparation for paving.
Grass restoration will be completed by the contractor prior to paving.
All paving is expected to be completed in early October.
Traffic Control
Mellum Drive and Christensen Way are closed to through traffic, but remain open to local traffic.