Mellum Drive Road Construction

Work Completed for Week 3: September 15 - September 19

  • The contractor completed all concrete replacements.

  • The City of Stoughton used its equipment and staff to pulverize the remaining asphalt pavement.

  • The City continued working on rough grading and removal of excess pulverized material.

Work Anticipated for Week 4: September 22 - September 26

  • The City of Stoughton will continue with excavation and placement of base course to address areas of unstable subgrade.

Upcoming Work

  • The contractor will adjust manhole castings and valve boxes to the new pavement elevation.

  • The contractor will fine grade the pulverized material in preparation for paving.

  • Grass restoration will be completed by the contractor prior to paving.

  • All paving is expected to be completed in early October.

Traffic Control

  • Mellum Drive and Christensen Way are closed to through traffic, but remain open to local traffic.