Work Completed for Week 10: August 18 - August 22

  • Heavy rain required cleanup by the contractor and delayed work planned for early in the week.

  • The City of Stoughton re-pulverized some areas due to re-solidification of the material resulting from traffic and moisture.

  • The Contractor continued with grading and rolling of pulverized material late in the week in preparation for paving.

  • The Contractor adjusted manhole castings and valve boxes to the new street elevations.

  • The contractor is schedule to pave the lower level of asphalt pavement on Saturday August 23rd.

Work Anticipated for Week 11: August 25 - August 29

  • The Contractor intends to place the upper layer of asphalt on Lincoln Avenue early in the week.

  • The contractor intends to finish grading activity on Wilson Street on Monday.

  • The contractor intends to complete paving on Wilson Street on Tuesday or Wednesday.

  • The contractor intends to complete all pavement markings by the end of next week.

Upcoming Work

  • The projects are expected to be substantially completed by August 29th. Only minor punch list work will remain after that date.

     

Traffic Control

  • Lincoln Avenue and Wilson Street are closed to through traffic, but open to local traffic.

  • Expect delays and driveway access challenges during paving on Lincoln Avenue.

  • Wilson Street is closed to through traffic, but open to local traffic.

Lincoln Ave Road Construction Project 2025