
Lincoln Avenue
Work Completed for Week 10: August 18 - August 22
Heavy rain required cleanup by the contractor and delayed work planned for early in the week.
The City of Stoughton re-pulverized some areas due to re-solidification of the material resulting from traffic and moisture.
The Contractor continued with grading and rolling of pulverized material late in the week in preparation for paving.
The Contractor adjusted manhole castings and valve boxes to the new street elevations.
The contractor is schedule to pave the lower level of asphalt pavement on Saturday August 23rd.
Work Anticipated for Week 11: August 25 - August 29
The Contractor intends to place the upper layer of asphalt on Lincoln Avenue early in the week.
The contractor intends to finish grading activity on Wilson Street on Monday.
The contractor intends to complete paving on Wilson Street on Tuesday or Wednesday.
The contractor intends to complete all pavement markings by the end of next week.
Upcoming Work
The projects are expected to be substantially completed by August 29th. Only minor punch list work will remain after that date.
Traffic Control
Lincoln Avenue and Wilson Street are closed to through traffic, but open to local traffic.
Expect delays and driveway access challenges during paving on Lincoln Avenue.
Wilson Street is closed to through traffic, but open to local traffic.