Lincoln Avenue
Scheduling
(Subject to Change)
June 12- Construction Start
June 16-July 1: Storm Sewer Work
June 30- July 11: From and Pour Concrete
July 16-17: Pulverization
July 16-21: Pulverized Material Removal
July 25-31- Fine Grade, Binder, Surface, Line Stripping
July 31- Construction Complete