Aug 25-Sept 8- Storm Sewer installation
Sept 22-Sept 29- Curb and Gutter installation
Sept 29-Oct 6 - Sidewalk and Driveway apron installation
Oct 6- Oct 20 - Asphalt paving
Oct 27- Pavement Marking
Oct 31- Project Completion